Wileman Engineers Limited in collaboration with Carrier Europe have recently installed an Ash Conveyor System for
Coventry & Solihull Waste Disposal Company.
The project demanded the removal of an old 1500mm Wide x 40 metre long Belt Conveyor underneath 3 incinerator Ash
Dischargers and its replacement with a Ampli-Flow Vibrating Feeder System supplied by the Belgion Company Carrier Europe.
The replacement was achieved within the stipulated 7 days to the Customers statisfaction.
Should you wish to have further information on this project please contact Matthew Joyce at the Wileman Head office at
Ashby de la Zouch or email cmjoyce@btconnect.com